The Phases of a Kitchen Remodel
Every kitchen job runs in the same order. The time each phase takes depends on what's changing, but the order rarely does, because each step sits on top of the one before it.
- 1. Design and planning: Measuring, layout, cabinet plan and material picks. Weeks for a refresh, longer when walls or plumbing move.
- 2. Ordering and permits: Cabinets, the countertop slab, appliances and fixtures are ordered, and permits are pulled. Cabinet lead time is usually the longest wait.
- 3. Demolition: The old kitchen comes out, often in a day or two.
- 4. Rough-in work: Any new plumbing, gas, electrical and framing, followed by inspections where permits apply.
- 5. Drywall and flooring: Walls are closed and patched; new flooring goes in if it runs under the cabinets.
- 6. Cabinets: Boxes are set level and fastened.
- 7. Countertops: Templated on the set cabinets, then fabricated and installed.
- 8. Backsplash and finish: Tile, lighting, plumbing fixtures, appliances, hardware and touch-ups.
Typical Time by Project Size
| Project | What changes | Construction time |
|---|---|---|
| Minor update | Cabinet refacing or paint, counters, backsplash | About 2 to 6 weeks |
| Mid-range remodel | New cabinets, counters and appliances, same layout | About 6 to 10 weeks |
| Full custom remodel | New layout, plumbing or walls moved | About 10 to 16 weeks or more |
Minor update
- What changes
- Cabinet refacing or paint, counters, backsplash
- Construction time
- About 2 to 6 weeks
Mid-range remodel
- What changes
- New cabinets, counters and appliances, same layout
- Construction time
- About 6 to 10 weeks
Full custom remodel
- What changes
- New layout, plumbing or walls moved
- Construction time
- About 10 to 16 weeks or more
Construction-time ranges from United Signature Construction's published guide. Planning and design come on top. We give you a schedule for your project after the design is set.
What Slows a Kitchen Remodel Down
- Cabinet lead times: Semi-custom and custom cabinets are built to order and are the longest wait on most jobs.
- Countertop templating: Stone can't be templated until the cabinets are set, so there's always a gap between the two.
- Changes mid-project: Changing a layout or a material after ordering restarts that part of the clock.
- Inspections: Permitted plumbing and electrical work has to pass inspection before walls are closed.
- Slab plumbing: In Dallas homes on a concrete slab, moving a drain means cutting and patching concrete.
- Surprises behind the walls: Old wiring, leaks or rot found during demolition need fixing before work goes on.
How to Keep Your Kitchen Remodel on Schedule
- Finish the design and pick every material before demolition starts.
- Order cabinets and appliances early, so they're on hand when the crew needs them.
- Decide on a sink and faucet before the counters are templated.
- Set up a temporary kitchen: a fridge, microwave and coffee maker in another room.
- Keep one point of contact so questions get answered the same day.
Keeping the layout is the biggest time saver. A cabinet refacing job skips demolition and rough-in entirely, and a good kitchen design phase keeps changes out of the build.
Asked often
Kitchen Remodel Timeline Questions
How long does a full kitchen remodel take?
Published guides put construction at about 6 to 12 weeks for a full remodel, after design and ordering. Layout changes, custom cabinets and permits make it longer.
Can I live in my house during a kitchen remodel?
Most people do. Plan a temporary kitchen in another room and expect dust and noise during demolition and rough-in.
How long are we without a kitchen?
From demolition until the counters and sink are in. Ordering everything before demolition keeps that stretch as short as it can be.
Why does it take so long to get countertops?
Stone is templated on the installed cabinets, then cut at the shop. That gap between cabinets and counters is built into every job.
Is cabinet refacing faster than new cabinets?
Yes. Refacing keeps the boxes and the layout, so there's no demolition, rough-in or new plumbing.
Sources
- Fixr, How Long Does a Kitchen Remodel Take? (January 13, 2025)
- Block Renovation, How Long Does a Kitchen Remodel Take?
- United Signature Construction, How Long Does a Kitchen Remodel Take? Timeline Explained
- Houzz, 2026 U.S. Houzz & Home Study (kitchen planning and construction time, 2025 projects)